![]() |
![]() |
| Home | News | Technologies | Journal | Forum | Conference | Advertisement | Contacts | ðóññêèé | / | english |
|
CHARACTERISTICS OF ASTRAKHAN GAS CONDENSATE FIELD (AGKM)
CT technologies are widely implemented by Schlumberger in Russia for cleanouts
of oil and gas wells as well as for production stimulation, logging and also drilling
the horizontal wells. CT operations in Astrakhan field are an example of successful
experience of CT intervention in highly sour high pressure/high temperature environment.
Astrakhan gas condensate field is extremely harsh in terms of highly corrosive
conditions, due to H2S concentration of up to 26% vol., bottom hole temperature of 110°C and formation
pressure as high as 600 bars. All this has a significant corrosive effect on downhole
equipment during well production and workover.
The field has been in production since the mid (dle) 80's and there is a tailpipe
100 to 200 meters long installed as a part of completion. The tailpipe (tubing)
is overlapping the production zone for 50-100 meters and there-fore highly susceptible
to corrosion. That corrosion of tubing metal can result in the coiled tubing becoming
stuck during CT operations. During well interventions with CT, the fluid is circulated
to the surface with flaring of gas phase after separation. It is not always possible
because of towns and villages located close to the field.
CT TECHNOLOGY IMPLEMENTATION FOR WELL WORKOVER IN AGKM
Despite the complications and specifics of AGKM field, CT technology has proven
its efficiency. First of all due to significantly lower damage of the near wellbore
area comparing to conventional workover, it is not necessary to kill the well
with high density drilling mud. At the same time it is required to separate gas
and solid phases in treating fluid at the surface, as well as to control contamination
of treating fluid with formation fluid. A complex approach that utilizes coiled
tubing together with well testing equipment meets all mentioned requirements and
also provides the following:
During the well clean out, treating fluid is delivered from surface tanks to
the coiled tubing string by high pressure triplex pumps. Flow back from the well
goes first through high pressure filters, then through the arrangement of manifolds,
gas separator and surge tank. The continuous process is provided by two elements
in high pressure filters. Fluid can be pumped through the plugged filtering element
to the special tank to remove collected solids.
Wellbore deposits can be removed in different ways, such as with conventional
five-orifice wash nozzle, high-jetting rotational tool or with positive displacement
downhole motor and bit. During well operations the main issue is CT exposure to
H2S. To minimize it, the production tubing is displaced with a water-methanol solution
(40%) before the CT run downhole. The following clean out is performed in slightly
overbalanced conditions with 5-10% fluid loss into the formation. Corrosion inhibitor
and H2S chemical scavenger are added to the treating fluid to minimize the effect of
corrosion.
It is important to provide the complete return of solids to surface during clean
out.
Before the operation, all conditions are modeled with design software to estimate
the range of critical parameters. During the treatment, sensor interface hardware
is used to monitor and record critical job data and also to estimate remaining
tubing life in real-time.
After wellbore clean out, matrix acidizing with hydrochloric acid takes place.
CT in that case allows placing acid across the zone of interest and also decreasing
volumes and operation time.
DESIGN OF OPERATION WITH COILED TUBING
At the design phase it is required first to define the sequence of techniques
that need to be implemented for deposits removal and wellbore clean out. It is
effective to run CT with a wash nozzle bottom hole assembly (BHA) to determine
the plug depth and also to clean out the unconsolidated plug. Acid can be pumped
at that stage to assist in plug removal. In case of hard consolidated plug, which
is insoluble in acid, a downhole motor can be used to mill out the plug and clean
the wellbore.
At the design stage the following data is critical:
With different job parameters, CoilCADE software is used to model CT string loads
in the wellbore, maximum weight on bit for milling operations and maximum CT tension
load. Distribution of these stresses on the CT string can be calculated at that
stage. The optimum regime of clean out is also calculated. With estimated CT loads
and also taking into consideration the impact of corrosive environments, the load
limits during the operation is calculated as well as the remaining CT life. Load
limits and CT life are monitored in real-time during the CT intervention. After
every operation an inspection of the coiled tubing string takes place to monitor
the damage to the CT string incurred in the wellbore.
CT IMPLEMENTATION EXPERIENCE: WELL # 840
Well history
A workover was performed to change tubular and wellhead equipment. The well was
killed and during the workover with conventional rig, high fluid loss/mud loss
occurred. To prevent and/or minimize these losses different (LCM) loss circulation
materials were pumped such as asbestos particles, cement and bentonite. Total
losses during the workover operation were as much as 720 m3.
A packer was installed and pressure tested. During flow back off the well fluid,
slugs of mud and gas were observed with tubing pressure drop. Due to unfavorable
weather conditions the flowback operation was suspended for 14 days. When flowback
resumed two plugs formed which were squeezed down to the formation. The flowback
operation was suspended again.
After resuming the flowback, another 4 plugs were removed by pressurizing / bleeding
off the pressure to a flare pit. Also chemical agents were pumped to assist in
plug removal. After that at the depth 3721 meters another plug was observed and
it wasn't removed by technique described above. Using bailing tubes the plug was
partially removed only down to 3772 meters. Lab analysis of plug material showed
it consisted of clay mud, cement and other LCM materials.
Schlumberger proposed Coiled tubing to clean out that well.
Job design with CoilCADET software
Estimated loads on coiled tubing string during well intervention
![]() ![]() Figure 2 shows the maximum calculated loads and also working loads versus pressure
difference between internal and external pressures.
![]() ![]() Figure 4 shows that most of the time, clean out is performed in overbalanced
conditions with successful transportation of solids to the surface. Annular velocity
during cleanout is not less than 40-50 m/min which is sufficient for solids transportation
to the surface in vertical well.
Well workover operation with coiled tubing
Despite the layout with number of units on wellsite, the units are mobile and
it is possible to rig down and leave the wellsite in short time. Complete equipment
rig up with pressure and function tests takes approximately 16 hours and complete
rig down takes approximately 12 hours.
CT operation description
Jet Blaster tool description
Jet Blaster tool is a rotating tool with high energy jetting effect. It is implemented
for deposits removal and consolidated plugs cleanout. It has some advantages,
such as high hydraulic energy on the nozzles, 360° coverage of the deposits during
cleanout, deposits removal in first run, controllable size of cuttings.
As a result of CT operations the plug was removed with acid squeeze and following
circulation with treating fluid. For stimulation of production matrix acidizing
of near wellbore area was performed following the removal of filter cake and clean
out of production zone with Jet Blaster. Production was restored from 0 to 150 000
m3 of gas per day. The plug on that well was removed by acid and a conventional
wash nozzle. If there's a consolidated hard plug, the positive displacement downhole
motor with mill can be used.
![]() CONCLUSIONS
Implementation of coiled tubing provides additional ways of well clean out and
production stimulation in Astrakhan gas condensate field. These methods are chemical
as well as mechanical with high-pressure jetting (Jet Blaster tool) and milling
(downhole motor). Coiled tubing avoids the need to kill the well prior to the
operation and therefore decreasing the damage of near wellbore area and also decreasing
the time of well stand by. Matrix acidizing through coiled tubing also has some
advantages such as increase of diversion effect by placing the coiled tubing string
at the depth of interest and using special diverting system based on viscoelastic
self-diverting acid (VDAT). Using Jet Blaster tool increase the efficiency of acidizing by equally distribution
of acid on whole production interval.
CT operations have some restrictions due to unfavorable weather conditions and
wind direction during the job. To perform operations independently from these
conditions it is possible to establish closed loop circulation system which requires
additional equipment. This technology is complicated to implement due to highly
sour formation fluid and co-operative actions of all parties are required for
success. CommentsFor posting your message please login or register |
| Home | News | Technologies | Journal | Forum | Conference | Advertisement | Contacts |
| All rights reserved Material from the site can be used with author's agreement only |
Galleria Tower 1 2700 Post Oak Boulevard, Suite 1400 |
Houston Texas 77056 USA Òåëåôîí:+1 281 657 3300 E-mail: cttimes@cttimes.org |
Ðàçðàáîòêà ñàéòà: Âåá-ñòóäèÿ Àëåêñàíäðà Ðåòþõèíà |