Almost all wells of Belorusneft are drilled ahead of schedule in January

17.02.2020
Courtesy of belorusneft.by

In January, Belorusneft built six wells in Belarus. Drilling was ongoing at the Kartashovskoye, Rechitskoye and Gartsevskoye fields.

At the Kartashovskoye field, the workers of the Svetlogorsk drilling department drilled well No. 15 17.2% faster than planned. Also, 9.8% ahead of schedule, we completed drilling of well No. 21 of the same area.

Rechitsa oil field was the most successful. Well No. 414 was drilled with a depth of 2,150 meters 15.5% ahead of schedule. Here, at the Rechitskoye field, the drillers constructed awell No. 507 14.3% ahead of schedule. Well No. 379 Rechitskaya was drilled 41.8% faster than planned.

Another well was drilled at Gartsevski field. This is exploration well No. 2s2 with a depth of 4,320 meters. It was here that deposits of the Sargaevsky, Voronezh and Semiluksky horizons were discovered and highly productive commercial oil inflows were obtained.