In Belorusneft-Siberia for 2.5 months twice updated their own achievements of daily drilling

03.06.2020
Courtesy of belorusneft.by

This is about operating drilling, which is carried out by Belorusneft- Siberia. Both achievements were accounted for by drilling crew No. 17. The team is led by foreman Vitaly Lakhurov. Workers are equipped with the ARS-200 mobile drilling unit manufactured by Gomel Seismotekhnika.

The team works at the Romanovskoye field, which is being developed by JSC Gazpromneft-Noyabrskneftegaz. On May 19, during the construction of production well No. 1106 Bush 5, 952 meters were completed per day. In total, according to the project, the well depth will be 4,325 meters.

The previous record among the drilling crews of Belorusneft- Siberia LLC also belongs to the team of Vitaly Lakhurov. It was this March. Then, at well No. 1105, during the drilling of the interval under the production casing, Belarusians drilled 698 meters of rocks per day. Now they were able to accelerate immediately by 30%.

Source: belorusneft.by